LEAD TIMES
How long will it take to get my order?
Greenheck publishes a weekly lead time schedule for most orders. The schedule is an estimation of time it takes to build products and breaks down the lead time by type and model of products. Products manufactured in multiple locations have the lead time broken down by each location.
Never wonder about your order status. Check the schedule anytime. As always, we want to help you win your bid; so, check with the factory if lead time is critical to the sale.
Never wonder about your order status. Check the schedule anytime. As always, we want to help you win your bid; so, check with the factory if lead time is critical to the sale.
US Manufacturing Lead Times
ESTIMATED US LEAD TIME SCHEDULE
---------Where lead times are critical to closing the order, check with the factory---------
1. Large orders, large quantities, and units requiring SDRs, special purchase motors, or international motors, may extend lead time
2. Orders will be scheduled based on longest lead time item.
Contact factory regarding capacity limits on Large Quick Build & Fast Pass orders.
Lead time Change Key: Lead Time Moved In - Lead Time Moved Out
Date Updated : December 10, 2023
0 | 1 | Product Category | Product Sub-Category | Model | Lead Time | |||
---|---|---|---|---|---|---|---|---|
Energy Recovery Units | Energy Recovery Units | ccc | MiniCores (5 & 10), MiniVents (450 & 750)ECVERV, ERVe, ERM (all except ERV-90 &-120)ERV-90, ERV-120GKD (curb only) | |||||
Energy Recovery Units | MiniCores (5 & 10), MiniVents (450 & 750) | 4 weeks | ||||||
Energy Recovery Units | ECV | Units configured with electric heaters will have extended lead times – check with the factory | ||||||
Energy Recovery Units | ECV | 6 Weeks | ||||||
Energy Recovery Units | c | ERV, ERVe, ERM (all except ERV-90 &-120)ERV-90, ERV-120GKD (curb only) | c | ERV, ERVe, ERM (all except ERV-90 &-120) | 6 Weeks | |||
Energy Recovery Units | c | ERV, ERVe, ERM (all except ERV-90 &-120)ERV-90, ERV-120GKD (curb only) | Units configured with electric heaters will have extended lead times – check with the factory | |||||
Energy Recovery Units | c | ERV-90, ERV-120 | Units configured with electric heaters will have extended lead times – check with the factory | |||||
Energy Recovery Units | c | ERV-90, ERV-120 | 6 Weeks | |||||
Energy Recovery Units | c | GKD (curb only) | 3 weeks | |||||
Dedicated Outdoor Air Systems | Dedicated Outdoor Air Systems | cccccc | RV-10RV-25, RV-45, RVE-40, RVE-85, RVC-35, and RVC-65RV-70, RVE-120, RV-75, and RVE-150RV-110 and RVE-180, and RVC-145GKD (curb only) | |||||
Dedicated Outdoor Air Systems | c | RV-10 | Units with electric heat may extend lead times up to 2 weeks | |||||
Dedicated Outdoor Air Systems | c | RV-10 | 7 Weeks | |||||
Dedicated Outdoor Air Systems | c | RV-25, RV-45, RVE-40, RVE-85, RVC-35, and RVC-65 | 15 weeks | |||||
Dedicated Outdoor Air Systems | c | RV-70, RVE-120, RV-75, and RVE-150 | 15 weeks | |||||
Dedicated Outdoor Air Systems | c | RV-110 and RVE-180, and RVC-145 | 13 Weeks | |||||
Dedicated Outdoor Air Systems | c | GKD (curb only) | 4 Weeks | |||||
Make-up Air Units | Make-up Air Units | ccccccccc | DG/KSF/MSFDGX/MSX (housing size 12-32) - Selected with none of the following: Coils, electric heat, hi-pro poly coating, recirculation units, service lights, SDRs.DGX/MSX (housing size 35) - Selected with none of the following: Coils, electric heat, recirculation units, service lights, SDRs.DGX/IGX/MSX (housing size 12-32)DGX/IGX/MSX (housing size 12-32) DG with Packaged DXDGX/IGX/MSX (housing size 35-42)TSU/TSF/VSU (housing size 2-50)GKD (curb only) | |||||
Make-up Air Units | c | DG/KSF/MSF | 4 Weeks | |||||
Make-up Air Units | c | DGX/MSX (housing size 12-32) - Selected with none of the following: Coils, electric heat, hi-pro poly coating, recirculation units, service lights, SDRs. | 4 Weeks | |||||
Make-up Air Units | c | DGX/MSX (housing size 35) - Selected with none of the following: Coils, electric heat, recirculation units, service lights, SDRs. | 4 Weeks | |||||
Make-up Air Units | c | DGX/IGX/MSX (housing size 12-32) | Units configured with coils may have longer lead times than posted – check with the factory for lead time critical orders. Units configured with electric heaters will have extended lead times – check with the factory for most up to date lead times. | |||||
Make-up Air Units | c | DGX/IGX/MSX (housing size 12-32) | 6 Weeks | |||||
Make-up Air Units | c | DGX/IGX/MSX (housing size 12-32) DG with Packaged DX | Units configured with electric heaters will have extended lead times – check with the factory | |||||
Make-up Air Units | c | DGX/IGX/MSX (housing size 12-32) DG with Packaged DX | 6 Weeks | |||||
Make-up Air Units | c | DGX/IGX/MSX (housing size 35-42) | 5 Weeks | |||||
Make-up Air Units | c | TSU/TSF/VSU (housing size 2-50) | 5 Weeks | |||||
Make-up Air Units | c | GKD (curb only) | 3 weeks | |||||
Indoor Air Handlers and Fan Coils | Indoor Air Handlers and Fan Coils | cc | ||||||
Indoor Air Handlers and Fan Coils | c | |||||||
Kitchen Ventilation | Kitchen Ventilation | cccccccccccccc | Kitchen Hoods (GO, GD 1-3, GX, GH-Exhaust only, and External Supply Plenums)Kitchen hoods (GW, GC, Backshelf, Single Island/V-Bank (all models), Double Island and Integral Supply Hoods)Controls- LegacyPrinted Circuit Board controls (DCV/CV)Crossover HoodControls with a VFD in KVS Utility CabinetAuto Scrubber Hood (GWAE)Utility Distribution Systems UDS***Grease Trapper (ESP)Grease Trapper (Modular PCU)Kitchen Pass ordersFire Ready HoodsSDR’s on any products (minimum)* | |||||
Kitchen Ventilation | c | Kitchen Hoods (GO, GD 1-3, GX, GH-Exhaust only, and External Supply Plenums) | 3 weeks | |||||
Kitchen Ventilation | c | Kitchen hoods (GW, GC, Backshelf, Single Island/V-Bank (all models), Double Island and Integral Supply Hoods) | 3 weeks | |||||
Kitchen Ventilation | c | Controls- Legacy | 3 Weeks | |||||
Kitchen Ventilation | c | Printed Circuit Board controls (DCV/CV) | 3 Weeks | |||||
Kitchen Ventilation | c | Crossover Hood | 3 Weeks | |||||
Kitchen Ventilation | c | Controls with a VFD in KVS Utility Cabinet | 4 Weeks | |||||
Kitchen Ventilation | c | Auto Scrubber Hood (GWAE) | 4 Weeks | |||||
Kitchen Ventilation | c | Utility Distribution Systems UDS*** | 6 Weeks | |||||
Kitchen Ventilation | c | Grease Trapper (ESP) | 6 Weeks | |||||
Kitchen Ventilation | c | Grease Trapper (Modular PCU) | 4 Weeks | |||||
Kitchen Ventilation | c | Kitchen Pass orders | 4 weeks | |||||
Kitchen Ventilation | c | Fire Ready Hoods | 2 weeks | |||||
Kitchen Ventilation | c | SDR’s on any products (minimum)* | 3 weeks | |||||
Kitchen Ventilation | *Except for SDR’s on 10 day list. Consult factory for estimated lead time. Unless requested in order entry notes, ALL KVS shipments will ship combined on the longest lead-time. ***Lead time on these products will begin once approved drawings have been received |
cccccccccccccc | Kitchen Hoods (GO, GD 1-3, GX, GH-Exhaust only, and External Supply Plenums)Kitchen hoods (GW, GC, Backshelf, Single Island/V-Bank (all models), Double Island and Integral Supply Hoods)Controls- LegacyPrinted Circuit Board controls (DCV/CV)Crossover HoodControls with a VFD in KVS Utility CabinetAuto Scrubber Hood (GWAE)Utility Distribution Systems UDS***Grease Trapper (ESP)Grease Trapper (Modular PCU)Kitchen Pass ordersFire Ready HoodsSDR’s on any products (minimum)* | |||||
Power Roof Ventilators (PRV) | Power Roof Ventilators (PRV) | cccccccccccccccc | Roof Curbs - MexicoRoof Curbs - WisconsinAll Painted Roof CurbsPipe PortalsGCCPRV Downblast (G, GB, GRS, RH, AE, AS)PRV Upblast (CUE, CUBE)Large Direct Drive PRV Fans (Upblast and Downblast), CUE 180-300 and G 240-300ALL PAINTED Large PRV Fans (CUBE 30" +, GB 26"+, RH 30"+, GRS 30 +)Large PRV Fans (CUBE 30" +, GB 26"+, RH 30"+, GRS 30 +)Painted PRV Fans less than size 300 (Includes USGF) NOTE: Macropoxy is extendedPRV Fans with certain TEFC Vari-Green motors (1HP 900 RPM, 3HP and larger) Not available on Fast PassMotor starters (NEMA-1, 3R and 4X enclosures)Motor starters (MSEM)Motor starters (MS-1P) | |||||
Power Roof Ventilators (PRV) | Fast Pass (Many of the PRV models below are Fast Pass Eligible if order is ALL Fast Pass) Fans = 7 Weeks; Curbs = 3 Weeks | cccccccccccccccc | Roof Curbs - MexicoRoof Curbs - WisconsinAll Painted Roof CurbsPipe PortalsGCCPRV Downblast (G, GB, GRS, RH, AE, AS)PRV Upblast (CUE, CUBE)Large Direct Drive PRV Fans (Upblast and Downblast), CUE 180-300 and G 240-300ALL PAINTED Large PRV Fans (CUBE 30" +, GB 26"+, RH 30"+, GRS 30 +)Large PRV Fans (CUBE 30" +, GB 26"+, RH 30"+, GRS 30 +)Painted PRV Fans less than size 300 (Includes USGF) NOTE: Macropoxy is extendedPRV Fans with certain TEFC Vari-Green motors (1HP 900 RPM, 3HP and larger) Not available on Fast PassMotor starters (NEMA-1, 3R and 4X enclosures)Motor starters (MSEM)Motor starters (MS-1P) | |||||
Power Roof Ventilators (PRV) | c | Roof Curbs - Mexico | 3 weeks | |||||
Power Roof Ventilators (PRV) | c | Roof Curbs - Wisconsin | 4 Weeks | |||||
Power Roof Ventilators (PRV) | c | All Painted Roof Curbs | 6 Weeks | |||||
Power Roof Ventilators (PRV) | c | Pipe Portals | 2 Weeks | |||||
Power Roof Ventilators (PRV) | c | GCC | 2 Weeks | |||||
Power Roof Ventilators (PRV) | c | PRV Downblast (G, GB, GRS, RH, AE, AS) | 8 Weeks | |||||
Power Roof Ventilators (PRV) | c | PRV Upblast (CUE, CUBE) | 8 Weeks | |||||
Power Roof Ventilators (PRV) | c | Large Direct Drive PRV Fans (Upblast and Downblast), CUE 180-300 and G 240-300 | 12 Weeks | |||||
Power Roof Ventilators (PRV) | c | ALL PAINTED Large PRV Fans (CUBE 30" +, GB 26"+, RH 30"+, GRS 30 +) | 12 weeeks | |||||
Power Roof Ventilators (PRV) | c | Large PRV Fans (CUBE 30" +, GB 26"+, RH 30"+, GRS 30 +) | 10 Weeks | |||||
Power Roof Ventilators (PRV) | c | Painted PRV Fans less than size 300 (Includes USGF) NOTE: Macropoxy is extended | 12 Weeks | |||||
Power Roof Ventilators (PRV) | c | PRV Fans with certain TEFC Vari-Green motors (1HP 900 RPM, 3HP and larger) Not available on Fast Pass | 12 - 17 weeks | |||||
Power Roof Ventilators (PRV) | c | Motor starters (NEMA-1, 3R and 4X enclosures) | 4 Weeks | |||||
Power Roof Ventilators (PRV) | c | Motor starters (NEMA-1, 3R and 4X enclosures) | Due to supply chain issues, Quick Builds are currently not available | |||||
Power Roof Ventilators (PRV) | c | Motor starters (MSEM) | 6 Weeks | |||||
Power Roof Ventilators (PRV) | c | Motor starters (MSEM) | Due to supply chain issues, Quick Builds are currently not available | |||||
Power Roof Ventilators (PRV) | c | Motor starters (MS-1P) | 14 Weeks | |||||
Power Roof Ventilators (PRV) | c | Motor starters (MS-1P) | Due to supply chain issues, Quick Builds are currently not available | |||||
Power Roof Ventilators (PRV) | We are experiencing ongoing supply chain issues with the motors listed below. *2HP and Greater Vari-Green motors *Standard AC motors used on G/CUE-90 and 95 fans QB availability will be removed from CAPS in the 4.40 release. Orders will be scheduled based on motor availability and may extend past posted lead times. PRV Fans with certain TEFC Vari-Green motors (1HP 900 RPM, 3HP and larger) may not be available on Fast Pass |
cccccccccccccccc | Roof Curbs - MexicoRoof Curbs - WisconsinAll Painted Roof CurbsPipe PortalsGCCPRV Downblast (G, GB, GRS, RH, AE, AS)PRV Upblast (CUE, CUBE)Large Direct Drive PRV Fans (Upblast and Downblast), CUE 180-300 and G 240-300ALL PAINTED Large PRV Fans (CUBE 30" +, GB 26"+, RH 30"+, GRS 30 +)Large PRV Fans (CUBE 30" +, GB 26"+, RH 30"+, GRS 30 +)Painted PRV Fans less than size 300 (Includes USGF) NOTE: Macropoxy is extendedPRV Fans with certain TEFC Vari-Green motors (1HP 900 RPM, 3HP and larger) Not available on Fast PassMotor starters (NEMA-1, 3R and 4X enclosures)Motor starters (MSEM)Motor starters (MS-1P) | |||||
Circulation | Circulation | ccccccccccc | HVLS Fans (DS: size 8’ to 24’)HVLS Fans (DC 8’ to 14’)HVLS Fans (DC 4’ to 7’)HVLS Controls (Standard Touchscreen)HVLS Controls (Keypad, Advanced Touchscreen)HVLS Northern Lights Fans (DC-5-NL)DM - 3DDFMac Fans (MAC)Industrial Circulators (IC) | |||||
Circulation | SDR lead times = 20 weeks | ccccccccccc | HVLS Fans (DS: size 8’ to 24’)HVLS Fans (DC 8’ to 14’)HVLS Fans (DC 4’ to 7’)HVLS Controls (Standard Touchscreen)HVLS Controls (Keypad, Advanced Touchscreen)HVLS Northern Lights Fans (DC-5-NL)DM - 3DDFMac Fans (MAC)Industrial Circulators (IC) | |||||
Circulation | c | HVLS Fans (DS: size 8’ to 24’) | 2.5 Weeks | |||||
Circulation | c | HVLS Fans (DC 8’ to 14’) | 2.5 Weeks | |||||
Circulation | c | HVLS Fans (DC 4’ to 7’) | 22 Weeks | |||||
Circulation | c | HVLS Fans (DC 4’ to 7’) | We are experiencing ongoing supply chain issues which may effect the posted lead time or the ability to ship on time | |||||
Circulation | c | HVLS Controls (Standard Touchscreen) | 2.5 Weeks | |||||
Circulation | c | HVLS Controls (Keypad, Advanced Touchscreen) | 2.5 Weeks | |||||
Circulation | c | HVLS Northern Lights Fans (DC-5-NL) | 2.5 Weeks | |||||
Circulation | c | DM - 3 | 2.5 Weeks | |||||
Circulation | c | DDF | 4 Weeks | |||||
Circulation | c | Mac Fans (MAC) | 3 weeks | |||||
Circulation | c | Mac Fans (MAC) | For any large orders, please consult the factory for a lead time due to shortages on guards | |||||
Circulation | c | Industrial Circulators (IC) | 3 weeks | |||||
Axial Fans | Axial Fans | ccccccccccccccccccccccccccccccccc | Fabra Hoods (FGI/FGR)Painted Fabra Hoods (FGI/FGR)Painted Rooftop, Sidewalls, Rooftop Upblast (54” and above)Small Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S, RCE/S; size 48” and below) - Ordered without factory mounted damperReversable Rooftop Fans (RPBR/F, RPDR/F)Small Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S, RCE/S; size 48” and below) - Ordered with factory mounted damperLarge Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S, RCE/S; size 54-60)Large Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 54” to 60”)Painted Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S; size 48” and below)Painted Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 20” to 48”) - Ordered without factory mounted damperPainted Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 20” to 48”) - Ordered with factory mounted damperExtra Large Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 72” ) - Ordered without factory dampersExtra Large Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 72” ) - Ordered with factory dampersExtra Large Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S; size 72”) - Ordered without factory dampersExtra Large Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S; size 72”) - Ordered with factory dampersMedium Rooftop Upblast Fans (RBU, RDU, RBUMO; size 48” and below)Large Rooftop Upblast Fans (RBU, RDU, RBUMO; size 54” and above)Small Sidewall Prop Fans (SE, SS; size 8” to 18”) - Ordered with factory mounted dampersSmall Sidewall Prop Fans (SE, SS; size 8” to 18”) - Ordered without factory dampersMedium Prop Fans (SE/S, SBE/S, SCE/S, SBCE/S, AER; size 20” to 48”) - Ordered with factory mounted dampersMedium Prop Fans (SE/S, SBE/S, SCE/S, SBCE/S, AER; size 20” to 48”) - Ordered without factory mounted dampersReversable Prop Fans (SCR, SBCR)Medium Prop Fans (BAER size 24" to 48")Weatherhoods (WTHD)Sidewall prop fans (SDPE)Condensor Fans (ARC)Motor starters (NEMA-1, 3R and 4X enclosures)Motor starters (MSEM)Motor starters (MS-1P)SDRsMatch Color Chip CoatingsVendor Applied Coatings | |||||
Axial Fans | Fast Pass (Many of the Axial models below are Fast Pass Eligible (if order is ALL Fast Pass) 3 weeks SDR lead times = 20 weeks |
ccccccccccccccccccccccccccccccccc | Fabra Hoods (FGI/FGR)Painted Fabra Hoods (FGI/FGR)Painted Rooftop, Sidewalls, Rooftop Upblast (54” and above)Small Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S, RCE/S; size 48” and below) - Ordered without factory mounted damperReversable Rooftop Fans (RPBR/F, RPDR/F)Small Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S, RCE/S; size 48” and below) - Ordered with factory mounted damperLarge Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S, RCE/S; size 54-60)Large Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 54” to 60”)Painted Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S; size 48” and below)Painted Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 20” to 48”) - Ordered without factory mounted damperPainted Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 20” to 48”) - Ordered with factory mounted damperExtra Large Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 72” ) - Ordered without factory dampersExtra Large Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 72” ) - Ordered with factory dampersExtra Large Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S; size 72”) - Ordered without factory dampersExtra Large Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S; size 72”) - Ordered with factory dampersMedium Rooftop Upblast Fans (RBU, RDU, RBUMO; size 48” and below)Large Rooftop Upblast Fans (RBU, RDU, RBUMO; size 54” and above)Small Sidewall Prop Fans (SE, SS; size 8” to 18”) - Ordered with factory mounted dampersSmall Sidewall Prop Fans (SE, SS; size 8” to 18”) - Ordered without factory dampersMedium Prop Fans (SE/S, SBE/S, SCE/S, SBCE/S, AER; size 20” to 48”) - Ordered with factory mounted dampersMedium Prop Fans (SE/S, SBE/S, SCE/S, SBCE/S, AER; size 20” to 48”) - Ordered without factory mounted dampersReversable Prop Fans (SCR, SBCR)Medium Prop Fans (BAER size 24" to 48")Weatherhoods (WTHD)Sidewall prop fans (SDPE)Condensor Fans (ARC)Motor starters (NEMA-1, 3R and 4X enclosures)Motor starters (MSEM)Motor starters (MS-1P)SDRsMatch Color Chip CoatingsVendor Applied Coatings | |||||
Axial Fans | c | Fabra Hoods (FGI/FGR) | 6 Weeks | |||||
Axial Fans | c | Painted Fabra Hoods (FGI/FGR) | 16 Weeks | |||||
Axial Fans | c | Painted Rooftop, Sidewalls, Rooftop Upblast (54” and above) | 4 Weeks | |||||
Axial Fans | c | Small Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S, RCE/S; size 48” and below) - Ordered without factory mounted damper | 6 Weeks | |||||
Axial Fans | c | Reversable Rooftop Fans (RPBR/F, RPDR/F) | 8 Weeks | |||||
Axial Fans | c | Small Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S, RCE/S; size 48” and below) - Ordered with factory mounted damper | 6 Weeks | |||||
Axial Fans | c | Large Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S, RCE/S; size 54-60) | 4 Weeks | |||||
Axial Fans | c | Large Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 54” to 60”) | 4 Weeks | |||||
Axial Fans | c | Painted Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S; size 48” and below) | 10 Weeks | |||||
Axial Fans | c | Painted Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 20” to 48”) - Ordered without factory mounted damper | 10 Weeks | |||||
Axial Fans | c | Painted Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 20” to 48”) - Ordered with factory mounted damper | 10 Weeks | |||||
Axial Fans | c | Extra Large Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 72” ) - Ordered without factory dampers | 4 Weeks | |||||
Axial Fans | c | Extra Large Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 72” ) - Ordered with factory dampers | 6 Weeks | |||||
Axial Fans | c | Extra Large Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S; size 72”) - Ordered without factory dampers | 4 Weeks | |||||
Axial Fans | c | Extra Large Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S; size 72”) - Ordered with factory dampers | 6 Weeks | |||||
Axial Fans | c | Medium Rooftop Upblast Fans (RBU, RDU, RBUMO; size 48” and below) | 4 Weeks | |||||
Axial Fans | c | Large Rooftop Upblast Fans (RBU, RDU, RBUMO; size 54” and above) | 4 Weeks | |||||
Axial Fans | c | Small Sidewall Prop Fans (SE, SS; size 8” to 18”) - Ordered with factory mounted dampers | 8 Weeks | |||||
Axial Fans | c | Small Sidewall Prop Fans (SE, SS; size 8” to 18”) - Ordered without factory dampers | 8 Weeks | |||||
Axial Fans | c | Medium Prop Fans (SE/S, SBE/S, SCE/S, SBCE/S, AER; size 20” to 48”) - Ordered with factory mounted dampers | 6 Weeks | |||||
Axial Fans | c | Medium Prop Fans (SE/S, SBE/S, SCE/S, SBCE/S, AER; size 20” to 48”) - Ordered without factory mounted dampers | 6 Weeks | |||||
Axial Fans | c | Reversable Prop Fans (SCR, SBCR) | 13 weeks | |||||
Axial Fans | c | Medium Prop Fans (BAER size 24" to 48") | 6 Weeks | |||||
Axial Fans | c | Weatherhoods (WTHD) | 6 Weeks | |||||
Axial Fans | c | Weatherhoods (WTHD) | Weatherhoods are primarily ordered as accessories for fans, please reference the lead time for the fan. If the Weatherhood is ordered as a stand-alone item please reference the posted lead time. |
|||||
Axial Fans | c | Sidewall prop fans (SDPE) | 4 Weeks | |||||
Axial Fans | c | Condensor Fans (ARC) | 4 Weeks | |||||
Axial Fans | c | Motor starters (NEMA-1, 3R and 4X enclosures) | 4 Weeks | |||||
Axial Fans | c | Motor starters (NEMA-1, 3R and 4X enclosures) | Due to supply chain issues, Quick Builds are currently not available | |||||
Axial Fans | c | Motor starters (MSEM) | 6 Weeks | |||||
Axial Fans | c | Motor starters (MSEM) | Due to supply chain issues, Quick Builds are currently not available | |||||
Axial Fans | c | Motor starters (MS-1P) | 14 Weeks | |||||
Axial Fans | c | Motor starters (MS-1P) | Due to supply chain issues, Quick Builds are currently not available | |||||
Axial Fans | c | SDRs | ||||||
Axial Fans | c | SDRs | Consult Factory for Lead Time | |||||
Axial Fans | c | Match Color Chip Coatings | ||||||
Axial Fans | c | Match Color Chip Coatings | Add 2-3 weeks to posted lead time | |||||
Axial Fans | c | Vendor Applied Coatings | ||||||
Axial Fans | c | Vendor Applied Coatings | Add 2-5 weeks to posted lead time | |||||
Axial Fans | Rooftops where the hoods are a separate line item, please reference the lead time for the Fabrahood. The order will ship at that lead time unless you would like to split the order and ship the fans and the Fabrahoods on separate delivery groups. | ccccccccccccccccccccccccccccccccc | Fabra Hoods (FGI/FGR)Painted Fabra Hoods (FGI/FGR)Painted Rooftop, Sidewalls, Rooftop Upblast (54” and above)Small Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S, RCE/S; size 48” and below) - Ordered without factory mounted damperReversable Rooftop Fans (RPBR/F, RPDR/F)Small Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S, RCE/S; size 48” and below) - Ordered with factory mounted damperLarge Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S, RCE/S; size 54-60)Large Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 54” to 60”)Painted Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S; size 48” and below)Painted Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 20” to 48”) - Ordered without factory mounted damperPainted Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 20” to 48”) - Ordered with factory mounted damperExtra Large Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 72” ) - Ordered without factory dampersExtra Large Prop Fans (SE/S, SBE/S, SCE/S/R, SBCE/S/R, AER; size 72” ) - Ordered with factory dampersExtra Large Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S; size 72”) - Ordered without factory dampersExtra Large Rooftop Fans (RBE/S/F, RBCE/S/F, RE/S; size 72”) - Ordered with factory dampersMedium Rooftop Upblast Fans (RBU, RDU, RBUMO; size 48” and below)Large Rooftop Upblast Fans (RBU, RDU, RBUMO; size 54” and above)Small Sidewall Prop Fans (SE, SS; size 8” to 18”) - Ordered with factory mounted dampersSmall Sidewall Prop Fans (SE, SS; size 8” to 18”) - Ordered without factory dampersMedium Prop Fans (SE/S, SBE/S, SCE/S, SBCE/S, AER; size 20” to 48”) - Ordered with factory mounted dampersMedium Prop Fans (SE/S, SBE/S, SCE/S, SBCE/S, AER; size 20” to 48”) - Ordered without factory mounted dampersReversable Prop Fans (SCR, SBCR)Medium Prop Fans (BAER size 24" to 48")Weatherhoods (WTHD)Sidewall prop fans (SDPE)Condensor Fans (ARC)Motor starters (NEMA-1, 3R and 4X enclosures)Motor starters (MSEM)Motor starters (MS-1P)SDRsMatch Color Chip CoatingsVendor Applied Coatings | |||||
Ceiling Fans | Ceiling Fans | ccccccccccccc | CRD-3XX series for use with Models SPSP-A (Size 70 to 290)SP-A (Sizes 390 to 1550)SP-B (All Sizes)CSP-A (All Sizes)SP/CSP-A390-VG, A510-VG, A710-VGSP-AP (All Models and Variants)SP-LP (All Models)Residential ERVS (ASSURE-120S-S1, SYNC-110SE-S1, SYNC-180SCE-S1, SYNC-270TCE-S1)SP-A50-90-VG-QD and MTO, SPA-90-130-VG-QD and MTO'sModels SP-A and SP-B with grille mounted motion sensorCoated Wall Caps (WC) | |||||
Ceiling Fans | Quick Delivery Program - Many Ceiling models are available within Greenheck's Quick Delivery Program | ccccccccccccc | CRD-3XX series for use with Models SPSP-A (Size 70 to 290)SP-A (Sizes 390 to 1550)SP-B (All Sizes)CSP-A (All Sizes)SP/CSP-A390-VG, A510-VG, A710-VGSP-AP (All Models and Variants)SP-LP (All Models)Residential ERVS (ASSURE-120S-S1, SYNC-110SE-S1, SYNC-180SCE-S1, SYNC-270TCE-S1)SP-A50-90-VG-QD and MTO, SPA-90-130-VG-QD and MTO'sModels SP-A and SP-B with grille mounted motion sensorCoated Wall Caps (WC) | |||||
Ceiling Fans | c | CRD-3XX series for use with Models SP | 2 Weeks | |||||
Ceiling Fans | c | SP-A (Size 70 to 290) | 2 weeks | |||||
Ceiling Fans | c | SP-A (Sizes 390 to 1550) | 2 weeks | |||||
Ceiling Fans | c | SP-B (All Sizes) | 2 weeks | |||||
Ceiling Fans | c | CSP-A (All Sizes) | 2 weeks | |||||
Ceiling Fans | c | SP/CSP-A390-VG, A510-VG, A710-VG | 2 weeks | |||||
Ceiling Fans | c | SP-AP (All Models and Variants) | 2 weeks | |||||
Ceiling Fans | c | SP-LP (All Models) | 2 Weeks | |||||
Ceiling Fans | c | Residential ERVS (ASSURE-120S-S1, SYNC-110SE-S1, SYNC-180SCE-S1, SYNC-270TCE-S1) | 9 Weeks | |||||
Ceiling Fans | c | SP-A50-90-VG-QD and MTO, SPA-90-130-VG-QD and MTO's | 12 weeks | |||||
Ceiling Fans | c | Models SP-A and SP-B with grille mounted motion sensor | 4 Weeks | |||||
Ceiling Fans | c | Coated Wall Caps (WC) | 13 weeks | |||||
Square Inline and Rooftop Centrifugal | Square Inline and Rooftop Centrifugal | cccccccccccccccccccc | Square Inline, Belt Drive, Centrifugal, All Construction (BSQ Size 70 - 240)Square Inline, Direct Drive, Centrifugal, Standard Construction (SQ 60 - 160) Galvanized construction w/ non-coated dampers, NEMA 1 disconnect or no switchSquare Inline, Direct Drive, Centrifugal,Non-Standard Construction (SQ 60 – 160) Painted or aluminum construction, SS fasteners, filtered, side discharge, non-standard motors (to include custom options, 575 v, EXP, or 50 C ambient)Square Inline, Direct Drive, Mixed Flow, Galvanized (SQ 7 - 16)Square Inline, Direct Drive, Mixed Flow, Galvanized (SQ 18-24)Rooftop Supply, Direct Drive, Mixed Flow, All Construction (KSQ 7-24)Rooftop Supply, Direct Drive, Mixed Flow and Square Inline, Direct Drive, Mixed Flow - All Construction (SQ & KSQ 27 - 33)Square Inline, Direct Drive, Mixed Flow, (SQ 18 - 24) - Non-Standard and filter sectionsSquare Inline, Direct Drive, Mixed Flow (SQ 7 - 16) - Non-Standard and filter sectionsSquare Inline, Belt Drive, Centrifugal, All Construction, Large Sizes (BSQ Size 300 – 420)Rooftop Exhaust, Belt Drive, Centrifugal, All Construction, Large Sizes (LB Size 42 – 54) Rooftop Supply, Belt Drive, Forward Curved, All Construction, Large Sizes (RSF Size 180 – 200, SAF Size 118 – 120)Cabinet, Belt Drive, Forward Curved, All Construction (BCF Size 106 - 212)Rooftop Exhaust, Belt Drive, Centrifugal, All Construction (LB Size 10 - 36) Rooftop Supply, Belt Drive, Forward Curved, All Construction (RSF 90 – 150, SAF Size 110 – 115) (Cook Eqv: 24 weeks)Motor starters (NEMA-1, 3R and 4X enclosures)Motor starters (MSEM)Motor starters (MS-1P)SDRsMatch Color Chip CoatingsVendor Applied Coatings | |||||
Square Inline and Rooftop Centrifugal | Fast Pass (Many of the Inline models below are Fast Pass Eligible (if order is ALL Fast Pass) 3 weeks SDR lead times = 20 weeks |
cccccccccccccccccccc | Square Inline, Belt Drive, Centrifugal, All Construction (BSQ Size 70 - 240)Square Inline, Direct Drive, Centrifugal, Standard Construction (SQ 60 - 160) Galvanized construction w/ non-coated dampers, NEMA 1 disconnect or no switchSquare Inline, Direct Drive, Centrifugal,Non-Standard Construction (SQ 60 – 160) Painted or aluminum construction, SS fasteners, filtered, side discharge, non-standard motors (to include custom options, 575 v, EXP, or 50 C ambient)Square Inline, Direct Drive, Mixed Flow, Galvanized (SQ 7 - 16)Square Inline, Direct Drive, Mixed Flow, Galvanized (SQ 18-24)Rooftop Supply, Direct Drive, Mixed Flow, All Construction (KSQ 7-24)Rooftop Supply, Direct Drive, Mixed Flow and Square Inline, Direct Drive, Mixed Flow - All Construction (SQ & KSQ 27 - 33)Square Inline, Direct Drive, Mixed Flow, (SQ 18 - 24) - Non-Standard and filter sectionsSquare Inline, Direct Drive, Mixed Flow (SQ 7 - 16) - Non-Standard and filter sectionsSquare Inline, Belt Drive, Centrifugal, All Construction, Large Sizes (BSQ Size 300 – 420)Rooftop Exhaust, Belt Drive, Centrifugal, All Construction, Large Sizes (LB Size 42 – 54) Rooftop Supply, Belt Drive, Forward Curved, All Construction, Large Sizes (RSF Size 180 – 200, SAF Size 118 – 120)Cabinet, Belt Drive, Forward Curved, All Construction (BCF Size 106 - 212)Rooftop Exhaust, Belt Drive, Centrifugal, All Construction (LB Size 10 - 36) Rooftop Supply, Belt Drive, Forward Curved, All Construction (RSF 90 – 150, SAF Size 110 – 115) (Cook Eqv: 24 weeks)Motor starters (NEMA-1, 3R and 4X enclosures)Motor starters (MSEM)Motor starters (MS-1P)SDRsMatch Color Chip CoatingsVendor Applied Coatings | |||||
Square Inline and Rooftop Centrifugal | c | Square Inline, Belt Drive, Centrifugal, All Construction (BSQ Size 70 - 240) | 4 Weeks | |||||
Square Inline and Rooftop Centrifugal | c | Square Inline, Direct Drive, Centrifugal, Standard Construction (SQ 60 - 160) Galvanized construction w/ non-coated dampers, NEMA 1 disconnect or no switch | 6 Weeks | |||||
Square Inline and Rooftop Centrifugal | c | Square Inline, Direct Drive, Centrifugal,Non-Standard Construction (SQ 60 – 160) Painted or aluminum construction, SS fasteners, filtered, side discharge, non-standard motors (to include custom options, 575 v, EXP, or 50 C ambient) | 8 Weeks | |||||
Square Inline and Rooftop Centrifugal | c | Square Inline, Direct Drive, Mixed Flow, Galvanized (SQ 7 - 16) | 4 Weeks | |||||
Square Inline and Rooftop Centrifugal | c | Square Inline, Direct Drive, Mixed Flow, Galvanized (SQ 7 - 16) | Quicks build currently are not available. They will land at standard lead times | |||||
Square Inline and Rooftop Centrifugal | c | Square Inline, Direct Drive, Mixed Flow, Galvanized (SQ 18-24) | 6 Weeks | |||||
Square Inline and Rooftop Centrifugal | c | Square Inline, Direct Drive, Mixed Flow, Galvanized (SQ 18-24) | Quicks build currently are not available. They will land at standard lead times | |||||
Square Inline and Rooftop Centrifugal | c | Rooftop Supply, Direct Drive, Mixed Flow, All Construction (KSQ 7-24) | 8 Weeks | |||||
Square Inline and Rooftop Centrifugal | c | Rooftop Supply, Direct Drive, Mixed Flow, All Construction (KSQ 7-24) | Quicks build currently are not available. They will land at standard lead times | |||||
Square Inline and Rooftop Centrifugal | c | Rooftop Supply, Direct Drive, Mixed Flow and Square Inline, Direct Drive, Mixed Flow - All Construction (SQ & KSQ 27 - 33) | 10 Weeks | |||||
Square Inline and Rooftop Centrifugal | c | Rooftop Supply, Direct Drive, Mixed Flow and Square Inline, Direct Drive, Mixed Flow - All Construction (SQ & KSQ 27 - 33) | Quicks build currently are not available. They will land at standard lead times | |||||
Square Inline and Rooftop Centrifugal | c | Square Inline, Direct Drive, Mixed Flow, (SQ 18 - 24) - Non-Standard and filter sections | 10 Weeks | |||||
Square Inline and Rooftop Centrifugal | c | Square Inline, Direct Drive, Mixed Flow, (SQ 18 - 24) - Non-Standard and filter sections | Quicks build currently are not available. They will land at standard lead times | |||||
Square Inline and Rooftop Centrifugal | c | Square Inline, Direct Drive, Mixed Flow (SQ 7 - 16) - Non-Standard and filter sections | 10 Weeks | |||||
Square Inline and Rooftop Centrifugal | c | Square Inline, Direct Drive, Mixed Flow (SQ 7 - 16) - Non-Standard and filter sections | Quicks build currently are not available. They will land at standard lead times | |||||
Square Inline and Rooftop Centrifugal | c | Square Inline, Belt Drive, Centrifugal, All Construction, Large Sizes (BSQ Size 300 – 420) | 4 Weeks | |||||
Square Inline and Rooftop Centrifugal | c | Rooftop Exhaust, Belt Drive, Centrifugal, All Construction, Large Sizes (LB Size 42 – 54) Rooftop Supply, Belt Drive, Forward Curved, All Construction, Large Sizes (RSF Size 180 – 200, SAF Size 118 – 120) | 4 Weeks | |||||
Square Inline and Rooftop Centrifugal | c | Cabinet, Belt Drive, Forward Curved, All Construction (BCF Size 106 - 212) | 9 Weeks | |||||
Square Inline and Rooftop Centrifugal | c | Rooftop Exhaust, Belt Drive, Centrifugal, All Construction (LB Size 10 - 36) Rooftop Supply, Belt Drive, Forward Curved, All Construction (RSF 90 – 150, SAF Size 110 – 115) (Cook Eqv: 24 weeks) | 9 Weeks | |||||
Square Inline and Rooftop Centrifugal | c | Motor starters (NEMA-1, 3R and 4X enclosures) | 4 Weeks | |||||
Square Inline and Rooftop Centrifugal | c | Motor starters (NEMA-1, 3R and 4X enclosures) | Due to supply chain issues, Quick Builds are currently not available | |||||
Square Inline and Rooftop Centrifugal | c | Motor starters (MSEM) | 6 Weeks | |||||
Square Inline and Rooftop Centrifugal | c | Motor starters (MSEM) | Due to supply chain issues, Quick Builds are currently not available | |||||
Square Inline and Rooftop Centrifugal | c | Motor starters (MS-1P) | 14 Weeks | |||||
Square Inline and Rooftop Centrifugal | c | Motor starters (MS-1P) | Due to supply chain issues, Quick Builds are currently not available | |||||
Square Inline and Rooftop Centrifugal | c | SDRs | ||||||
Square Inline and Rooftop Centrifugal | c | SDRs | Consult Factory for Lead Time | |||||
Square Inline and Rooftop Centrifugal | c | Match Color Chip Coatings | ||||||
Square Inline and Rooftop Centrifugal | c | Match Color Chip Coatings | Add 2-3 weeks to posted lead time | |||||
Square Inline and Rooftop Centrifugal | c | Vendor Applied Coatings | ||||||
Square Inline and Rooftop Centrifugal | c | Vendor Applied Coatings | Add 2-5 weeks to posted lead time | |||||
Tubular Inline | Tubular Inline | cccccccccc | Large Fan AX-160 TAUB/TBI-60Inline Mixed Flow (QEI, QEID, QEID-FJ)Propeller Upblast Exhaust (TAUB, TAUD)Tube Axial (TBI-CA, TBI-FS, TDI, AX, GJX)Centrifugal Jet (GJI)Vane Axial High Pressure, Belt Drive (VAB)Vane Axial High Pressure Direct Drive (VAD) (based on motor availability)Orders with SDRs, Union Made required or Extended Lead-TimesVFDs and Controls - Tubular Inline | |||||
Tubular Inline | c | Large Fan AX-160 TAUB/TBI-60 | 24 weeks | |||||
Tubular Inline | c | Inline Mixed Flow (QEI, QEID, QEID-FJ) | 24 weeks | |||||
Tubular Inline | c | Propeller Upblast Exhaust (TAUB, TAUD) | 24 weeks | |||||
Tubular Inline | c | Tube Axial (TBI-CA, TBI-FS, TDI, AX, GJX) | 24 weeks | |||||
Tubular Inline | c | Centrifugal Jet (GJI) | 22 weeks | |||||
Tubular Inline | c | Vane Axial High Pressure, Belt Drive (VAB) | 29 weeks | |||||
Tubular Inline | c | Vane Axial High Pressure Direct Drive (VAD) (based on motor availability) | 29 weeks | |||||
Tubular Inline | c | Orders with SDRs, Union Made required or Extended Lead-Times | Consult Factory for Lead Time | |||||
Tubular Inline | c | Orders with SDRs, Union Made required or Extended Lead-Times | Non-standard motors, international motors or other long lead-time purchased parts may extend order lead-time | |||||
Tubular Inline | c | VFDs and Controls - Tubular Inline | 26 weeks | |||||
Lab Exhaust | Lab Exhaust | cccccccccccccccccccc | High Plume, Tubular Centrifugal (VK-H -Belt)High Plume, Tubular Centrifugal (VK-H – Direct)Variable Nozzle, Tubular Centrifugal (VK-HS)High Plume, Dilution Mixed Flow (VK-MH, VK-MD - Belt)High Plume, Dilution Mixed Flow (VK-MH, VK-MD - Direct)Variable Nozzle, Dilution Mixed Flow (VK-MS - Belt)High Plume, Dilution Mixed flow (belt) VKCURBSVariable Nozzle, Dilution Mixed Flow (VK-MS - Direct)High Plume Dilution Mixed Flow (Direct) VKCURBSHigh Plume, Dilution Centrifugal (VK-CH, VK-CD - Belt)Energy Recovery (VK-M Compact Sizes 5,8,15 ) VKERS CURBSHigh Plume, Dilution Centrifugal (VK-CH, VK-CD - Direct)Variable Nozzle, Dilution Centrifugal VK-CS - Belt)Variable Nozzle, Dilution Centrifugal VK-CS - Direct)Energy Recovery (VK-C Series ERS)Energy Recovery (VK-M Compact, Sizes 5,8,15)Energy Recovery (VK-M Standard, Sizes 20,30,40,60)Energy Recovery (VK-M Standard Sizes 20.30,40,60 ) VKERS CURBSVFDs and Controls - Lab Exhaust | |||||
Lab Exhaust | c | High Plume, Tubular Centrifugal (VK-H -Belt) | 24 weeks | |||||
Lab Exhaust | c | High Plume, Tubular Centrifugal (VK-H – Direct) | 28 weeks | |||||
Lab Exhaust | c | Variable Nozzle, Tubular Centrifugal (VK-HS) | 25 weeks | |||||
Lab Exhaust | c | High Plume, Dilution Mixed Flow (VK-MH, VK-MD - Belt) | 25 weeks | |||||
Lab Exhaust | c | High Plume, Dilution Mixed Flow (VK-MH, VK-MD - Direct) | 29 weeks | |||||
Lab Exhaust | c | Variable Nozzle, Dilution Mixed Flow (VK-MS - Belt) | 25 weeks | |||||
Lab Exhaust | c | High Plume, Dilution Mixed flow (belt) VKCURBS | 15 weeks | |||||
Lab Exhaust | c | Variable Nozzle, Dilution Mixed Flow (VK-MS - Direct) | 29 weeks | |||||
Lab Exhaust | c | High Plume Dilution Mixed Flow (Direct) VKCURBS | 15 weeks | |||||
Lab Exhaust | c | High Plume, Dilution Centrifugal (VK-CH, VK-CD - Belt) | 25 weeks | |||||
Lab Exhaust | c | Energy Recovery (VK-M Compact Sizes 5,8,15 ) VKERS CURBS | 15 weeks | |||||
Lab Exhaust | c | High Plume, Dilution Centrifugal (VK-CH, VK-CD - Direct) | 29 weeks | |||||
Lab Exhaust | c | Variable Nozzle, Dilution Centrifugal VK-CS - Belt) | 25 weeks | |||||
Lab Exhaust | c | Variable Nozzle, Dilution Centrifugal VK-CS - Direct) | 29 weeks | |||||
Lab Exhaust | c | Energy Recovery (VK-C Series ERS) | 30 weeks | |||||
Lab Exhaust | c | Energy Recovery (VK-M Compact, Sizes 5,8,15) | 27 weeks | |||||
Lab Exhaust | c | Energy Recovery (VK-M Standard, Sizes 20,30,40,60) | 22 weeks | |||||
Lab Exhaust | c | Energy Recovery (VK-M Standard Sizes 20.30,40,60 ) VKERS CURBS | 25 weeks | |||||
Lab Exhaust | c | VFDs and Controls - Lab Exhaust | 26 weeks | |||||
Lab Exhaust | Lead-time Notes: 1. Any SDR (fan or motor) will add an additional 2-3 weeks to standard lead-time for review and engineering, and are processed on a first in/first out basis. 2. Standard lead-time does not start until the order is released to production. 3. Add an additional 2-5 weeks to standard lead-time for units with vendor applied coatings (dependent on vendor selected) 4. Coatings other than standard Concrete Gray could result in additional lead-time (consult factory) 5. Non-standard motors, international motors or other long lead-time purchased components may extend order lead-time past standard 6. VKCURBS of QTY of 5 or more (consult factory for lead-time) |
cccccccccccccccccccc | High Plume, Tubular Centrifugal (VK-H -Belt)High Plume, Tubular Centrifugal (VK-H – Direct)Variable Nozzle, Tubular Centrifugal (VK-HS)High Plume, Dilution Mixed Flow (VK-MH, VK-MD - Belt)High Plume, Dilution Mixed Flow (VK-MH, VK-MD - Direct)Variable Nozzle, Dilution Mixed Flow (VK-MS - Belt)High Plume, Dilution Mixed flow (belt) VKCURBSVariable Nozzle, Dilution Mixed Flow (VK-MS - Direct)High Plume Dilution Mixed Flow (Direct) VKCURBSHigh Plume, Dilution Centrifugal (VK-CH, VK-CD - Belt)Energy Recovery (VK-M Compact Sizes 5,8,15 ) VKERS CURBSHigh Plume, Dilution Centrifugal (VK-CH, VK-CD - Direct)Variable Nozzle, Dilution Centrifugal VK-CS - Belt)Variable Nozzle, Dilution Centrifugal VK-CS - Direct)Energy Recovery (VK-C Series ERS)Energy Recovery (VK-M Compact, Sizes 5,8,15)Energy Recovery (VK-M Standard, Sizes 20,30,40,60)Energy Recovery (VK-M Standard Sizes 20.30,40,60 ) VKERS CURBSVFDs and Controls - Lab Exhaust | |||||
Centrifugal | Centrifugal | ccccccccc | Utility Set Fan Gen2 (Model USF-XX-B6, B7, A2, F3)Utility Set Fan (Model USF-XX-B1, B2, B3, B4, B5, A1, F1, or F2, includes FJC/FJI)Fan Arrays (MOA, HPA)Plenum Fans (APD, APM, APH)Industrial Fans (IPA, IPW, IPO, PLG)Light Duty Pressure Blower (FPB)Fiberglass Reinforced Plastic (BCSW-FRP)*Orders with SDRs, Union Made required or Extended Lead-Times | |||||
Centrifugal | c | Utility Set Fan Gen2 (Model USF-XX-B6, B7, A2, F3) | 18 weeks | |||||
Centrifugal | c | Utility Set Fan (Model USF-XX-B1, B2, B3, B4, B5, A1, F1, or F2, includes FJC/FJI) | 24 weeks | |||||
Centrifugal | c | Fan Arrays (MOA, HPA) | 24 weeks | |||||
Centrifugal | c | Plenum Fans (APD, APM, APH) | 24 weeks | |||||
Centrifugal | c | Industrial Fans (IPA, IPW, IPO, PLG) | 24 weeks | |||||
Centrifugal | c | Light Duty Pressure Blower (FPB) | 12 weeks | |||||
Centrifugal | c | Fiberglass Reinforced Plastic (BCSW-FRP) | Consult Factory for Lead Time | |||||
Centrifugal | c | *Orders with SDRs, Union Made required or Extended Lead-Times | Consult Factory for Lead Time | |||||
Centrifugal | Lead-time Notes: 1. Any SDR (fan or motor) will add an additional 2-3 weeks to standard lead-time for review and engineering, and are processed on a first in/first out basis. 2. Standard lead-time does not start until the order is released to production. 3. Add an additional 2-5 weeks to standard lead-time for units with vendor applied coatings (dependent on vendor selected) 4. Coatings other than standard Concrete Gray could result in additional lead-time (consult factory) 5. Non-standard motors, international motors or other long lead-time purchased components may extend order lead-time past standard 6. VKCURBS of QTY of 5 or more (consult factory for lead-time) |
ccccccccc | Utility Set Fan Gen2 (Model USF-XX-B6, B7, A2, F3)Utility Set Fan (Model USF-XX-B1, B2, B3, B4, B5, A1, F1, or F2, includes FJC/FJI)Fan Arrays (MOA, HPA)Plenum Fans (APD, APM, APH)Industrial Fans (IPA, IPW, IPO, PLG)Light Duty Pressure Blower (FPB)Fiberglass Reinforced Plastic (BCSW-FRP)*Orders with SDRs, Union Made required or Extended Lead-Times | |||||
Air Terminal Units | Air Terminal Units | ccccccccc | Single Duct - No Heat (XG-TH-500, XG-TL-500, XG-BP-600)Single Duct - Hot Water Heat (XG-TH-500, XG-TL-500)Single Duct - Electric Heat (XG-TH-500, XG-TL-500)Fan Powered - No Heat (XG-FCI-600, XG-FCL-600, XG-FCQ-700, XG,FVI-500, XG-FVL-600)Fan Powered - Hot Water (XG-FCI-600, XG-FCL-600, XG-FCQ-700, XG,FVI-500, XG-FVL-600)Fan Powered - Electric Heat (XG-FCI-600, XG-FCL-600, XG-FCQ-700, XG,FVI-500, XG-FVL-600)Dual Duct (XG-DD-500, XG-DH-500, XG-DS-600)Retrofit (XG-SR-500, XG-RT-500, XG-RA-500) | |||||
Air Terminal Units | c | Single Duct - No Heat (XG-TH-500, XG-TL-500, XG-BP-600) | 2 weeks | |||||
Air Terminal Units | c | Single Duct - Hot Water Heat (XG-TH-500, XG-TL-500) | 3 Weeks | |||||
Air Terminal Units | c | Single Duct - Electric Heat (XG-TH-500, XG-TL-500) | 4 weeks | |||||
Air Terminal Units | c | Fan Powered - No Heat (XG-FCI-600, XG-FCL-600, XG-FCQ-700, XG,FVI-500, XG-FVL-600) | 2 weeks | |||||
Air Terminal Units | c | Fan Powered - Hot Water (XG-FCI-600, XG-FCL-600, XG-FCQ-700, XG,FVI-500, XG-FVL-600) | 3 Weeks | |||||
Air Terminal Units | c | Fan Powered - Electric Heat (XG-FCI-600, XG-FCL-600, XG-FCQ-700, XG,FVI-500, XG-FVL-600) | 4 weeks | |||||
Air Terminal Units | c | Dual Duct (XG-DD-500, XG-DH-500, XG-DS-600) | 2 weeks | |||||
Air Terminal Units | c | Retrofit (XG-SR-500, XG-RT-500, XG-RA-500) | 3 weeks | |||||
Dampers | Dampers | cccccccccccccccccccccc | Control Dampers (VCD-2X, VCD-3X, MBD-15, FBH, FBV, SEVCD, VCDRM)Control Dampers - Extruded (VCD-4X)Control Dampers - Thermally Broken (ICD)Smoke and Fire/Smoke Dampers (FSD, SMD, DFD-210, DFDAF)Round Dampers (FSDR, SMDR, DFDR, FDR, VCDR, MBDR, RBDR, CRD-501, WDR-53, SSWDR-53, ABD-Z1/Z2)Backdraft Dampers - Extruded (EM, GM)Curtain Fire Dampers (FD, DFD, SSFD, SSDFD, CRD-60, ABD-FD)Backdraft Dampers (Non-stock Configurations of WD200, 300, 400)Backdraft Dampers (Non-stock Configurations of WD100)Backdraft Dampers (Non-stock Configurations of BD)Relief Dampers (BR, PR)Air Measuring Dampers (AMD, AMS)Automatic Balancing Dampers (ABD)Ceiling Radiation Dampers (CRD - Reference Ceiling Fans for 3XX Series, MBD-10, RBD-10, ABD-RB)Cable Operated Radial Blade Dampers (BTDR-50)Heavy Duty Dampers (HB, HBS, HCD, HPR, HSD, Vektor)Heavy Duty Round Dampers (HBDR, HBTR, HCDR, HBT)Heavy Duty Dampers (HTOD)Duct Heaters (IDHB, IDHE)Outdoor Duct Heaters (IDHE-O)Access and Pressure Relief Doors (CAD, HAD, RAD, PRAD, VRAD) | |||||
Dampers | Total Lead Time = Submission Drawings + Engineering + Paint + Production Lead Time Submission Drawings = 2 Weeks Engineering SDR's = 2 Weeks Standard Paint Lead Time = 1 Week Custom Color Match Lead Time = 3 Weeks Large orders, large quantities, special purchase motors, or international motors, may extend lead time Fast Pass = 10 Days |
cccccccccccccccccccccc | Control Dampers (VCD-2X, VCD-3X, MBD-15, FBH, FBV, SEVCD, VCDRM)Control Dampers - Extruded (VCD-4X)Control Dampers - Thermally Broken (ICD)Smoke and Fire/Smoke Dampers (FSD, SMD, DFD-210, DFDAF)Round Dampers (FSDR, SMDR, DFDR, FDR, VCDR, MBDR, RBDR, CRD-501, WDR-53, SSWDR-53, ABD-Z1/Z2)Backdraft Dampers - Extruded (EM, GM)Curtain Fire Dampers (FD, DFD, SSFD, SSDFD, CRD-60, ABD-FD)Backdraft Dampers (Non-stock Configurations of WD200, 300, 400)Backdraft Dampers (Non-stock Configurations of WD100)Backdraft Dampers (Non-stock Configurations of BD)Relief Dampers (BR, PR)Air Measuring Dampers (AMD, AMS)Automatic Balancing Dampers (ABD)Ceiling Radiation Dampers (CRD - Reference Ceiling Fans for 3XX Series, MBD-10, RBD-10, ABD-RB)Cable Operated Radial Blade Dampers (BTDR-50)Heavy Duty Dampers (HB, HBS, HCD, HPR, HSD, Vektor)Heavy Duty Round Dampers (HBDR, HBTR, HCDR, HBT)Heavy Duty Dampers (HTOD)Duct Heaters (IDHB, IDHE)Outdoor Duct Heaters (IDHE-O)Access and Pressure Relief Doors (CAD, HAD, RAD, PRAD, VRAD) | |||||
Dampers | c | Control Dampers (VCD-2X, VCD-3X, MBD-15, FBH, FBV, SEVCD, VCDRM) | 4 Weeks | |||||
Dampers | c | Control Dampers - Extruded (VCD-4X) | 3 Weeks | |||||
Dampers | c | Control Dampers - Thermally Broken (ICD) | 3 Weeks | |||||
Dampers | c | Smoke and Fire/Smoke Dampers (FSD, SMD, DFD-210, DFDAF) | 5 Weeks | |||||
Dampers | c | Round Dampers (FSDR, SMDR, DFDR, FDR, VCDR, MBDR, RBDR, CRD-501, WDR-53, SSWDR-53, ABD-Z1/Z2) | 6 Weeks | |||||
Dampers | c | Backdraft Dampers - Extruded (EM, GM) | 2 Weeks | |||||
Dampers | c | Curtain Fire Dampers (FD, DFD, SSFD, SSDFD, CRD-60, ABD-FD) | 4 Weeks | |||||
Dampers | c | Backdraft Dampers (Non-stock Configurations of WD200, 300, 400) | 7 Weeks | |||||
Dampers | c | Backdraft Dampers (Non-stock Configurations of WD100) | 5 Weeks | |||||
Dampers | c | Backdraft Dampers (Non-stock Configurations of BD) | 5 Weeks | |||||
Dampers | c | Relief Dampers (BR, PR) | 2 Weeks | |||||
Dampers | c | Air Measuring Dampers (AMD, AMS) | 4 Weeks | |||||
Dampers | c | Automatic Balancing Dampers (ABD) | 3 Weeks | |||||
Dampers | c | Ceiling Radiation Dampers (CRD - Reference Ceiling Fans for 3XX Series, MBD-10, RBD-10, ABD-RB) | 4 Weeks | |||||
Dampers | c | Cable Operated Radial Blade Dampers (BTDR-50) | 4 Weeks | |||||
Dampers | c | Heavy Duty Dampers (HB, HBS, HCD, HPR, HSD, Vektor) | 5 Weeks | |||||
Dampers | c | Heavy Duty Round Dampers (HBDR, HBTR, HCDR, HBT) | 8 Weeks | |||||
Dampers | c | Heavy Duty Dampers (HTOD) | 9 Weeks | |||||
Dampers | c | Duct Heaters (IDHB, IDHE) | 3 Weeks | |||||
Dampers | c | Duct Heaters (IDHB, IDHE) | Duct Heater QB order cutoff time is 10:00 A.M. | |||||
Dampers | c | Outdoor Duct Heaters (IDHE-O) | 8 Weeks | |||||
Dampers | c | Access and Pressure Relief Doors (CAD, HAD, RAD, PRAD, VRAD) | 4 Weeks | |||||
Dampers | Industrial grade actuators (even in CAPs) may have longer lead time If lead time is critical, please consult factory |
cccccccccccccccccccccc | Control Dampers (VCD-2X, VCD-3X, MBD-15, FBH, FBV, SEVCD, VCDRM)Control Dampers - Extruded (VCD-4X)Control Dampers - Thermally Broken (ICD)Smoke and Fire/Smoke Dampers (FSD, SMD, DFD-210, DFDAF)Round Dampers (FSDR, SMDR, DFDR, FDR, VCDR, MBDR, RBDR, CRD-501, WDR-53, SSWDR-53, ABD-Z1/Z2)Backdraft Dampers - Extruded (EM, GM)Curtain Fire Dampers (FD, DFD, SSFD, SSDFD, CRD-60, ABD-FD)Backdraft Dampers (Non-stock Configurations of WD200, 300, 400)Backdraft Dampers (Non-stock Configurations of WD100)Backdraft Dampers (Non-stock Configurations of BD)Relief Dampers (BR, PR)Air Measuring Dampers (AMD, AMS)Automatic Balancing Dampers (ABD)Ceiling Radiation Dampers (CRD - Reference Ceiling Fans for 3XX Series, MBD-10, RBD-10, ABD-RB)Cable Operated Radial Blade Dampers (BTDR-50)Heavy Duty Dampers (HB, HBS, HCD, HPR, HSD, Vektor)Heavy Duty Round Dampers (HBDR, HBTR, HCDR, HBT)Heavy Duty Dampers (HTOD)Duct Heaters (IDHB, IDHE)Outdoor Duct Heaters (IDHE-O)Access and Pressure Relief Doors (CAD, HAD, RAD, PRAD, VRAD) | |||||
Louvers | Louvers | cAcousticalAcousticalBrick VentsBrick VentsEquipment ScreensEquipment ScreensStationary Extruded AluminumStationary Extruded AluminumStationary FEMA LouverStationary FEMA LouverLouvered PenthousesLouvered PenthousesLouvered PenthousesOperable Extruded AluminumOperable Extruded AluminumThinlineThinlineProducts With Welded Construction | AFA, AFJ,BVE, BVFEESEDD, EDJ, EHH, EHM, EHV, ESD, ESJ, ESS, EVH, SED, SEH, SES, EDK, ESKAFLESD-635PD, EHH-601PDWIH, WRHEAC, EACA, EACC, EAD, EAH, ECD, GCE,ESJ-155, ESU | |||||
Louvers | Lead time shown include 1 week for paint or anodize finish (deduct 1 week if mill finish). Larger orders may extend lead times beyond that shown (consult factory if desired) Engineered Submittal Drawings (If Required): 2-3 weeks (depending on scope) Engineering Lead Time For SDR Orders: 2-3 weeks (depending on scope) *Add engineering lead time to production lead time for approximate total lead time Custom Color Matching: 3 weeks (does not include time for customer approval) *Orders with custom color will not be released for production without approval *Reduce lead time by proceeding with custom color match and customer approval prior to release during submittal phase *Fast Pass = 10 Days (15 Days if Painted) |
cAcousticalAcousticalBrick VentsBrick VentsEquipment ScreensEquipment ScreensStationary Extruded AluminumStationary Extruded AluminumStationary FEMA LouverStationary FEMA LouverLouvered PenthousesLouvered PenthousesLouvered PenthousesOperable Extruded AluminumOperable Extruded AluminumThinlineThinlineProducts With Welded Construction | AFA, AFJ,BVE, BVFEESEDD, EDJ, EHH, EHM, EHV, ESD, ESJ, ESS, EVH, SED, SEH, SES, EDK, ESKAFLESD-635PD, EHH-601PDWIH, WRHEAC, EACA, EACC, EAD, EAH, ECD, GCE,ESJ-155, ESU | |||||
Louvers | Acoustical | AFA, AFJ, | Acoustical | |||||
Louvers | Acoustical | AFA, AFJ, | 5 Weeks | |||||
Louvers | Brick Vents | BVE, BVF | Brick Vents | |||||
Louvers | Brick Vents | BVE, BVF | 4 weeks | |||||
Louvers | Equipment Screens | EES | Equipment Screens | |||||
Louvers | Equipment Screens | EES | 5 Weeks | |||||
Louvers | Stationary Extruded Aluminum | EDD, EDJ, EHH, EHM, EHV, ESD, ESJ, ESS, EVH, SED, SEH, SES, EDK, ESK | Stationary Extruded Aluminum | |||||
Louvers | Stationary Extruded Aluminum | EDD, EDJ, EHH, EHM, EHV, ESD, ESJ, ESS, EVH, SED, SEH, SES, EDK, ESK | 5 Weeks | |||||
Louvers | Stationary FEMA Louver | AFL | Stationary FEMA Louver | |||||
Louvers | Stationary FEMA Louver | AFL | 5 Weeks | |||||
Louvers | Louvered Penthouses | ESD-635PD, EHH-601PDWIH, WRH | Louvered Penthouses | |||||
Louvers | Louvered Penthouses | ESD-635PD, EHH-601PD | 5 Weeks | |||||
Louvers | Louvered Penthouses | WIH, WRH | 5 Weeks | |||||
Louvers | Operable Extruded Aluminum | EAC, EACA, EACC, EAD, EAH, ECD, GCE, | Operable Extruded Aluminum | |||||
Louvers | Operable Extruded Aluminum | EAC, EACA, EACC, EAD, EAH, ECD, GCE, | 5 Weeks | |||||
Louvers | Thinline | ESJ-155, ESU | Thinline | |||||
Louvers | Thinline | ESJ-155, ESU | 5 Weeks | |||||
Louvers | Products With Welded Construction | Products With Welded Construction | 5 Weeks | |||||
Louvers | Louver lead times as shown are typical as based on our normal blend of business and may fluctuate inward or outward depending on material availability. | cAcousticalAcousticalBrick VentsBrick VentsEquipment ScreensEquipment ScreensStationary Extruded AluminumStationary Extruded AluminumStationary FEMA LouverStationary FEMA LouverLouvered PenthousesLouvered PenthousesLouvered PenthousesOperable Extruded AluminumOperable Extruded AluminumThinlineThinlineProducts With Welded Construction | AFA, AFJ,BVE, BVFEESEDD, EDJ, EHH, EHM, EHV, ESD, ESJ, ESS, EVH, SED, SEH, SES, EDK, ESKAFLESD-635PD, EHH-601PDWIH, WRHEAC, EACA, EACC, EAD, EAH, ECD, GCE,ESJ-155, ESU | |||||
Grilles, Registers & Diffusers | Grilles, Registers & Diffusers | Supply GrillesSupply GrillesSupply GrillesReturn GrillesReturn GrillesReturn GrillesReturn GrillesFilter GrillesFilter GrillesFilter GrillesFilter GrillesHeavy Duty GrillesHeavy Duty GrillesHeavy Duty GrillesDoor/Transfer GrillesDoor/Transfer GrillesSpiral Duct GrillesSpiral Duct GrillesSpiral Duct GrillesSpiral Duct GrillesSpiral Duct GrillesIndustrial GrillesIndustrial GrillesIndustrial GrillesSpecialty GrillesSpecialty GrillesSpecialty GrillesSpecialty GrillesDirectional Ceiling DiffusersDirectional Ceiling DiffusersDirectional Ceiling DiffusersDirectional Ceiling DiffusersDirectional Ceiling DiffusersDirectional Ceiling DiffusersPerforated Ceiling DiffusersPerforated Ceiling DiffusersPerforated Ceiling DiffusersPerforated Ceiling DiffusersPerforated Ceiling DiffusersPerforated Ceiling DiffusersPerforated Ceiling DiffusersRound Ceiling DiffusersRound Ceiling DiffusersRound Ceiling DiffusersArchitectural DiffusersArchitectural DiffusersArchitectural DiffusersVAV Ceiling DiffusersVAV Ceiling DiffusersVAV Ceiling DiffusersLinear Diffusers & GrillesLinear Diffusers & GrillesLinear Diffusers & GrillesLinear Diffusers & GrillesLinear Diffusers & GrillesLinear Diffusers & GrillesPlenum Slot DiffusersPlenum Slot DiffusersPlenum Slot DiffusersPlenum Slot DiffusersDisplacement DiffusersDisplacement DiffusersEngineered Polymer ProductsEngineered Polymer ProductsFire Rated ProductsFire Rated ProductsSecurity ProductsSecurity ProductsStainless Steel Products | Ceiling/Sidewall Supply grilles (Series XG-L/XG-V/XG-4000)Sidewall Supply with Air Foil Blades (Series XG-4000-AF)Return Grilles (Series XG-RH/XG-SRH/XG-RHE/XG-4000R)Egg crate Return (Series XG-CC5/XG-CC1/XG-CC15/XG-CC45)Perforated Face Return (Series XG-RPF)Filter Return Grilles (Series XG-RHF/XG-RHEF/XG-SRHF)Egg crate Return Filter Grille (Series XG-CC5F)Perforated /Face Filter Grille (Series XG-RPF)Sidewall Return Heavy Duty (Series XG-HDRH)Steel Gym Grille (Series XG-4500)Door Grille (Series XG-DG)Universal Mount Spiral Duct Grilles (Series XG-4000P)Curved Flange Spiral Duct Grilles (Series XG-4000PCF)Spiral Duct Mount Linear Slot Diffuser (Series XG-6600SP)Spiral Duct Mount Drum Louver (Series XG-RL-SP)High Capacity Grille (Series XG-4100/XG-4200/XG-4300)Drum Louver (Series XG-RL)Jet Aire (Series XG-JA)Punkah Louver (Series XG-MPK)Round (Series XG-MR)Directional Louver Face Diffusers (Series XG-5000/XG-5500/XG-9000)Concentric Supply / Return Diffuser (Series XG-DAF-CC5)Square Cone Diffusers (Series XG-5700/XG-5800)Square Plaque Face Diffuser (Series XG-5750)High performance Plaque Face Diffuser (Series XG-Phenominator)Curved Blade pattern Controller (Series XG-7000)Non Ducted Return (Series XG-PRTB)Fiberglass Back pan (Series XG-7300)Face Mounted Pattern Controller (Series XG-7500)Neck Mounted Pattern Controller (Series XG-7600)Modular Core (Series XG-7900)Round Ceiling Diffusers (Series XG-3000/XG-3100/XG-3200)Architectural Round Plaque Face Diffuser (Model XG-R5750)Louver Face (Series XG-5500DD)Modular Slot (Series XG-6600SQ)Thermal VAV Diffusers (Series XG-MSC)Electronic VAV Diffusers (Series XG-MSE)Linear Slot Diffuers (Series XG-6600)Formations Linear Diffusers (Series XG-AFL)Linear Bar Grilles (Series XG-2000)Louver Face Linear (Series XG-LFL)Universal PlenumsAdjustable Pattern Controller (Series XG-PHP)High Capacity Fixed Pattern Controller (Series XG-PHC)Light Troffer Diffusers (Series XG-LT)Displacement Diffusers (Series XG-DD)Engineered Polymer Products (Series XG-EP)Fire Rated Packages (Series XG-FRS)Security Grilles (Series XG-SG) | |||||
Grilles, Registers & Diffusers | Lead times are manufacturing days and exclude transit time. | Supply GrillesSupply GrillesSupply GrillesReturn GrillesReturn GrillesReturn GrillesReturn GrillesFilter GrillesFilter GrillesFilter GrillesFilter GrillesHeavy Duty GrillesHeavy Duty GrillesHeavy Duty GrillesDoor/Transfer GrillesDoor/Transfer GrillesSpiral Duct GrillesSpiral Duct GrillesSpiral Duct GrillesSpiral Duct GrillesSpiral Duct GrillesIndustrial GrillesIndustrial GrillesIndustrial GrillesSpecialty GrillesSpecialty GrillesSpecialty GrillesSpecialty GrillesDirectional Ceiling DiffusersDirectional Ceiling DiffusersDirectional Ceiling DiffusersDirectional Ceiling DiffusersDirectional Ceiling DiffusersDirectional Ceiling DiffusersPerforated Ceiling DiffusersPerforated Ceiling DiffusersPerforated Ceiling DiffusersPerforated Ceiling DiffusersPerforated Ceiling DiffusersPerforated Ceiling DiffusersPerforated Ceiling DiffusersRound Ceiling DiffusersRound Ceiling DiffusersRound Ceiling DiffusersArchitectural DiffusersArchitectural DiffusersArchitectural DiffusersVAV Ceiling DiffusersVAV Ceiling DiffusersVAV Ceiling DiffusersLinear Diffusers & GrillesLinear Diffusers & GrillesLinear Diffusers & GrillesLinear Diffusers & GrillesLinear Diffusers & GrillesLinear Diffusers & GrillesPlenum Slot DiffusersPlenum Slot DiffusersPlenum Slot DiffusersPlenum Slot DiffusersDisplacement DiffusersDisplacement DiffusersEngineered Polymer ProductsEngineered Polymer ProductsFire Rated ProductsFire Rated ProductsSecurity ProductsSecurity ProductsStainless Steel Products | Ceiling/Sidewall Supply grilles (Series XG-L/XG-V/XG-4000)Sidewall Supply with Air Foil Blades (Series XG-4000-AF)Return Grilles (Series XG-RH/XG-SRH/XG-RHE/XG-4000R)Egg crate Return (Series XG-CC5/XG-CC1/XG-CC15/XG-CC45)Perforated Face Return (Series XG-RPF)Filter Return Grilles (Series XG-RHF/XG-RHEF/XG-SRHF)Egg crate Return Filter Grille (Series XG-CC5F)Perforated /Face Filter Grille (Series XG-RPF)Sidewall Return Heavy Duty (Series XG-HDRH)Steel Gym Grille (Series XG-4500)Door Grille (Series XG-DG)Universal Mount Spiral Duct Grilles (Series XG-4000P)Curved Flange Spiral Duct Grilles (Series XG-4000PCF)Spiral Duct Mount Linear Slot Diffuser (Series XG-6600SP)Spiral Duct Mount Drum Louver (Series XG-RL-SP)High Capacity Grille (Series XG-4100/XG-4200/XG-4300)Drum Louver (Series XG-RL)Jet Aire (Series XG-JA)Punkah Louver (Series XG-MPK)Round (Series XG-MR)Directional Louver Face Diffusers (Series XG-5000/XG-5500/XG-9000)Concentric Supply / Return Diffuser (Series XG-DAF-CC5)Square Cone Diffusers (Series XG-5700/XG-5800)Square Plaque Face Diffuser (Series XG-5750)High performance Plaque Face Diffuser (Series XG-Phenominator)Curved Blade pattern Controller (Series XG-7000)Non Ducted Return (Series XG-PRTB)Fiberglass Back pan (Series XG-7300)Face Mounted Pattern Controller (Series XG-7500)Neck Mounted Pattern Controller (Series XG-7600)Modular Core (Series XG-7900)Round Ceiling Diffusers (Series XG-3000/XG-3100/XG-3200)Architectural Round Plaque Face Diffuser (Model XG-R5750)Louver Face (Series XG-5500DD)Modular Slot (Series XG-6600SQ)Thermal VAV Diffusers (Series XG-MSC)Electronic VAV Diffusers (Series XG-MSE)Linear Slot Diffuers (Series XG-6600)Formations Linear Diffusers (Series XG-AFL)Linear Bar Grilles (Series XG-2000)Louver Face Linear (Series XG-LFL)Universal PlenumsAdjustable Pattern Controller (Series XG-PHP)High Capacity Fixed Pattern Controller (Series XG-PHC)Light Troffer Diffusers (Series XG-LT)Displacement Diffusers (Series XG-DD)Engineered Polymer Products (Series XG-EP)Fire Rated Packages (Series XG-FRS)Security Grilles (Series XG-SG) | |||||
Grilles, Registers & Diffusers | Supply Grilles | Ceiling/Sidewall Supply grilles (Series XG-L/XG-V/XG-4000)Sidewall Supply with Air Foil Blades (Series XG-4000-AF) | Supply Grilles | |||||
Grilles, Registers & Diffusers | Supply Grilles | Ceiling/Sidewall Supply grilles (Series XG-L/XG-V/XG-4000) | 3 weeks | |||||
Grilles, Registers & Diffusers | Supply Grilles | Sidewall Supply with Air Foil Blades (Series XG-4000-AF) | 4 weeks | |||||
Grilles, Registers & Diffusers | Supply Grilles | Sidewall Supply with Air Foil Blades (Series XG-4000-AF) | Quick build requests require prior approval. | |||||
Grilles, Registers & Diffusers | Return Grilles | Return Grilles (Series XG-RH/XG-SRH/XG-RHE/XG-4000R)Egg crate Return (Series XG-CC5/XG-CC1/XG-CC15/XG-CC45)Perforated Face Return (Series XG-RPF) | Return Grilles | |||||
Grilles, Registers & Diffusers | Return Grilles | Return Grilles (Series XG-RH/XG-SRH/XG-RHE/XG-4000R) | 3 weeks | |||||
Grilles, Registers & Diffusers | Return Grilles | Egg crate Return (Series XG-CC5/XG-CC1/XG-CC15/XG-CC45) | 3 weeks | |||||
Grilles, Registers & Diffusers | Return Grilles | Perforated Face Return (Series XG-RPF) | 3 weeks | |||||
Grilles, Registers & Diffusers | Filter Grilles | Filter Return Grilles (Series XG-RHF/XG-RHEF/XG-SRHF)Egg crate Return Filter Grille (Series XG-CC5F)Perforated /Face Filter Grille (Series XG-RPF) | Filter Grilles | |||||
Grilles, Registers & Diffusers | Filter Grilles | Filter Return Grilles (Series XG-RHF/XG-RHEF/XG-SRHF) | 3 weeks | |||||
Grilles, Registers & Diffusers | Filter Grilles | Egg crate Return Filter Grille (Series XG-CC5F) | 3 weeks | |||||
Grilles, Registers & Diffusers | Filter Grilles | Perforated /Face Filter Grille (Series XG-RPF) | 3 weeks | |||||
Grilles, Registers & Diffusers | Heavy Duty Grilles | Sidewall Return Heavy Duty (Series XG-HDRH)Steel Gym Grille (Series XG-4500) | Heavy Duty Grilles | |||||
Grilles, Registers & Diffusers | Heavy Duty Grilles | Sidewall Return Heavy Duty (Series XG-HDRH) | 3 weeks | |||||
Grilles, Registers & Diffusers | Heavy Duty Grilles | Steel Gym Grille (Series XG-4500) | 3 weeks | |||||
Grilles, Registers & Diffusers | Door/Transfer Grilles | Door Grille (Series XG-DG) | Door/Transfer Grilles | |||||
Grilles, Registers & Diffusers | Door/Transfer Grilles | Door Grille (Series XG-DG) | 3 weeks | |||||
Grilles, Registers & Diffusers | Spiral Duct Grilles | Universal Mount Spiral Duct Grilles (Series XG-4000P)Curved Flange Spiral Duct Grilles (Series XG-4000PCF)Spiral Duct Mount Linear Slot Diffuser (Series XG-6600SP)Spiral Duct Mount Drum Louver (Series XG-RL-SP) | Spiral Duct Grilles | |||||
Grilles, Registers & Diffusers | Spiral Duct Grilles | Universal Mount Spiral Duct Grilles (Series XG-4000P) | 3 weeks | |||||
Grilles, Registers & Diffusers | Spiral Duct Grilles | Curved Flange Spiral Duct Grilles (Series XG-4000PCF) | 3 weeks | |||||
Grilles, Registers & Diffusers | Spiral Duct Grilles | Spiral Duct Mount Linear Slot Diffuser (Series XG-6600SP) | 3 weeks | |||||
Grilles, Registers & Diffusers | Spiral Duct Grilles | Spiral Duct Mount Linear Slot Diffuser (Series XG-6600SP) | Quick build requests require prior approval. | |||||
Grilles, Registers & Diffusers | Spiral Duct Grilles | Spiral Duct Mount Drum Louver (Series XG-RL-SP) | 5 weeks | |||||
Grilles, Registers & Diffusers | Spiral Duct Grilles | Spiral Duct Mount Drum Louver (Series XG-RL-SP) | Quick build requests require prior approval. | |||||
Grilles, Registers & Diffusers | Industrial Grilles | High Capacity Grille (Series XG-4100/XG-4200/XG-4300)Drum Louver (Series XG-RL) | Industrial Grilles | |||||
Grilles, Registers & Diffusers | Industrial Grilles | High Capacity Grille (Series XG-4100/XG-4200/XG-4300) | 3 weeks | |||||
Grilles, Registers & Diffusers | Industrial Grilles | Drum Louver (Series XG-RL) | 3 weeks | |||||
Grilles, Registers & Diffusers | Specialty Grilles | Jet Aire (Series XG-JA)Punkah Louver (Series XG-MPK)Round (Series XG-MR) | Specialty Grilles | |||||
Grilles, Registers & Diffusers | Specialty Grilles | Jet Aire (Series XG-JA) | 3 weeks | |||||
Grilles, Registers & Diffusers | Specialty Grilles | Jet Aire (Series XG-JA) | Quick builds are unavailable. | |||||
Grilles, Registers & Diffusers | Specialty Grilles | Punkah Louver (Series XG-MPK) | 3 weeks | |||||
Grilles, Registers & Diffusers | Specialty Grilles | Punkah Louver (Series XG-MPK) | Quick builds are unavailable. | |||||
Grilles, Registers & Diffusers | Specialty Grilles | Round (Series XG-MR) | 3 weeks | |||||
Grilles, Registers & Diffusers | Directional Ceiling Diffusers | Directional Louver Face Diffusers (Series XG-5000/XG-5500/XG-9000)Concentric Supply / Return Diffuser (Series XG-DAF-CC5)Square Cone Diffusers (Series XG-5700/XG-5800)Square Plaque Face Diffuser (Series XG-5750)High performance Plaque Face Diffuser (Series XG-Phenominator) | Directional Ceiling Diffusers | |||||
Grilles, Registers & Diffusers | Directional Ceiling Diffusers | Directional Louver Face Diffusers (Series XG-5000/XG-5500/XG-9000) | 3 weeks | |||||
Grilles, Registers & Diffusers | Directional Ceiling Diffusers | Concentric Supply / Return Diffuser (Series XG-DAF-CC5) | 3 weeks | |||||
Grilles, Registers & Diffusers | Directional Ceiling Diffusers | Square Cone Diffusers (Series XG-5700/XG-5800) | 3 weeks | |||||
Grilles, Registers & Diffusers | Directional Ceiling Diffusers | Square Plaque Face Diffuser (Series XG-5750) | 3 weeks | |||||
Grilles, Registers & Diffusers | Directional Ceiling Diffusers | High performance Plaque Face Diffuser (Series XG-Phenominator) | 4 weeks | |||||
Grilles, Registers & Diffusers | Perforated Ceiling Diffusers | Curved Blade pattern Controller (Series XG-7000)Non Ducted Return (Series XG-PRTB)Fiberglass Back pan (Series XG-7300)Face Mounted Pattern Controller (Series XG-7500)Neck Mounted Pattern Controller (Series XG-7600)Modular Core (Series XG-7900) | Perforated Ceiling Diffusers | |||||
Grilles, Registers & Diffusers | Perforated Ceiling Diffusers | Curved Blade pattern Controller (Series XG-7000) | 3 weeks | |||||
Grilles, Registers & Diffusers | Perforated Ceiling Diffusers | Non Ducted Return (Series XG-PRTB) | 3 weeks | |||||
Grilles, Registers & Diffusers | Perforated Ceiling Diffusers | Fiberglass Back pan (Series XG-7300) | 3 weeks | |||||
Grilles, Registers & Diffusers | Perforated Ceiling Diffusers | Face Mounted Pattern Controller (Series XG-7500) | 3 weeks | |||||
Grilles, Registers & Diffusers | Perforated Ceiling Diffusers | Neck Mounted Pattern Controller (Series XG-7600) | 3 weeks | |||||
Grilles, Registers & Diffusers | Perforated Ceiling Diffusers | Modular Core (Series XG-7900) | 3 weeks | |||||
Grilles, Registers & Diffusers | Round Ceiling Diffusers | Round Ceiling Diffusers (Series XG-3000/XG-3100/XG-3200)Architectural Round Plaque Face Diffuser (Model XG-R5750) | Round Ceiling Diffusers | |||||
Grilles, Registers & Diffusers | Round Ceiling Diffusers | Round Ceiling Diffusers (Series XG-3000/XG-3100/XG-3200) | 3 weeks | |||||
Grilles, Registers & Diffusers | Round Ceiling Diffusers | Architectural Round Plaque Face Diffuser (Model XG-R5750) | 3 weeks | |||||
Grilles, Registers & Diffusers | Architectural Diffusers | Louver Face (Series XG-5500DD)Modular Slot (Series XG-6600SQ) | Architectural Diffusers | |||||
Grilles, Registers & Diffusers | Architectural Diffusers | Louver Face (Series XG-5500DD) | 4 weeks | |||||
Grilles, Registers & Diffusers | Architectural Diffusers | Modular Slot (Series XG-6600SQ) | 3 weeks | |||||
Grilles, Registers & Diffusers | VAV Ceiling Diffusers | Thermal VAV Diffusers (Series XG-MSC)Electronic VAV Diffusers (Series XG-MSE) | VAV Ceiling Diffusers | |||||
Grilles, Registers & Diffusers | VAV Ceiling Diffusers | Thermal VAV Diffusers (Series XG-MSC) | 3 weeks | |||||
Grilles, Registers & Diffusers | VAV Ceiling Diffusers | Electronic VAV Diffusers (Series XG-MSE) | 3 weeks | |||||
Grilles, Registers & Diffusers | Linear Diffusers & Grilles | Linear Slot Diffuers (Series XG-6600)Formations Linear Diffusers (Series XG-AFL)Linear Bar Grilles (Series XG-2000)Louver Face Linear (Series XG-LFL)Universal Plenums | Linear Diffusers & Grilles | |||||
Grilles, Registers & Diffusers | Linear Diffusers & Grilles | Linear Slot Diffuers (Series XG-6600) | 3 weeks | |||||
Grilles, Registers & Diffusers | Linear Diffusers & Grilles | Linear Slot Diffuers (Series XG-6600) | NOTE: Quick build requests will require prior approval. | |||||
Grilles, Registers & Diffusers | Linear Diffusers & Grilles | Formations Linear Diffusers (Series XG-AFL) | 3 weeks | |||||
Grilles, Registers & Diffusers | Linear Diffusers & Grilles | Linear Bar Grilles (Series XG-2000) | 3 weeks | |||||
Grilles, Registers & Diffusers | Linear Diffusers & Grilles | Louver Face Linear (Series XG-LFL) | 3 weeks | |||||
Grilles, Registers & Diffusers | Linear Diffusers & Grilles | Universal Plenums | 3 weeks | |||||
Grilles, Registers & Diffusers | Plenum Slot Diffusers | Adjustable Pattern Controller (Series XG-PHP)High Capacity Fixed Pattern Controller (Series XG-PHC)Light Troffer Diffusers (Series XG-LT) | Plenum Slot Diffusers | |||||
Grilles, Registers & Diffusers | Plenum Slot Diffusers | Adjustable Pattern Controller (Series XG-PHP) | 3 weeks | |||||
Grilles, Registers & Diffusers | Plenum Slot Diffusers | High Capacity Fixed Pattern Controller (Series XG-PHC) | 3 weeks | |||||
Grilles, Registers & Diffusers | Plenum Slot Diffusers | Light Troffer Diffusers (Series XG-LT) | 4 weeks | |||||
Grilles, Registers & Diffusers | Plenum Slot Diffusers | Light Troffer Diffusers (Series XG-LT) | Quick Builds are unavailable. | |||||
Grilles, Registers & Diffusers | Displacement Diffusers | Displacement Diffusers (Series XG-DD) | Displacement Diffusers | |||||
Grilles, Registers & Diffusers | Displacement Diffusers | Displacement Diffusers (Series XG-DD) | 8 weeks | |||||
Grilles, Registers & Diffusers | Displacement Diffusers | Displacement Diffusers (Series XG-DD) | Quick build requests require prior approval. | |||||
Grilles, Registers & Diffusers | Engineered Polymer Products | Engineered Polymer Products (Series XG-EP) | Engineered Polymer Products | |||||
Grilles, Registers & Diffusers | Engineered Polymer Products | Engineered Polymer Products (Series XG-EP) | 4 weeks | |||||
Grilles, Registers & Diffusers | Engineered Polymer Products | Engineered Polymer Products (Series XG-EP) | Quick build requests require prior approval. | |||||
Grilles, Registers & Diffusers | Fire Rated Products | Fire Rated Packages (Series XG-FRS) | Fire Rated Products | |||||
Grilles, Registers & Diffusers | Fire Rated Products | Fire Rated Packages (Series XG-FRS) | 4 weeks | |||||
Grilles, Registers & Diffusers | Fire Rated Products | Fire Rated Packages (Series XG-FRS) | Quick build requests require prior approval. | |||||
Grilles, Registers & Diffusers | Security Products | Security Grilles (Series XG-SG) | Security Products | |||||
Grilles, Registers & Diffusers | Security Products | Security Grilles (Series XG-SG) | 5 weeks | |||||
Grilles, Registers & Diffusers | Security Products | Security Grilles (Series XG-SG) | Quick build requests require prior approval. | |||||
Grilles, Registers & Diffusers | Stainless Steel Products | Stainless Steel Products | 5-6 weeks | |||||
Healthcare, Laboratories, and Cleanrooms | Healthcare, Laboratories, and Cleanrooms | Non-filtered DiffusersNon-filtered DiffusersFiltered DiffusersFiltered DiffusersOperating Room SystemsOperating Room SystemsOperating Room Systems with Structual Equipment SupportsOperating Room Systems with Structual Equipment SupportsFan Filter DiffusersFan Filter DiffusersHigh-efficency Filters (HLC-FILTER)High-efficency Filters (HLC-FILTER)High-efficency Filters (HLC-FILTER) | HLC-LFD, HLC-CLF, HLC-FFR, HLC-HC4HLC-GSL, HLC-GFRHLC-SAC, HLC-HCG, HLC-MPAHLC-SPAHLC-FPS, HLC-FPR, HLC-FPI, HLC-FPCStocked HEPA filters (48x24, 48x12, 36x24, 24x24)ULPA, High Flow HEPA, & non-stocked HEPA Filters | |||||
Healthcare, Laboratories, and Cleanrooms | Lead times are manufacturing days and exclude transit time. | Non-filtered DiffusersNon-filtered DiffusersFiltered DiffusersFiltered DiffusersOperating Room SystemsOperating Room SystemsOperating Room Systems with Structual Equipment SupportsOperating Room Systems with Structual Equipment SupportsFan Filter DiffusersFan Filter DiffusersHigh-efficency Filters (HLC-FILTER)High-efficency Filters (HLC-FILTER)High-efficency Filters (HLC-FILTER) | HLC-LFD, HLC-CLF, HLC-FFR, HLC-HC4HLC-GSL, HLC-GFRHLC-SAC, HLC-HCG, HLC-MPAHLC-SPAHLC-FPS, HLC-FPR, HLC-FPI, HLC-FPCStocked HEPA filters (48x24, 48x12, 36x24, 24x24)ULPA, High Flow HEPA, & non-stocked HEPA Filters | |||||
Healthcare, Laboratories, and Cleanrooms | Stainless Steel Products | Quick build requests require prior approval. | ||||||
Healthcare, Laboratories, and Cleanrooms | Non-filtered Diffusers | HLC-LFD, HLC-CLF, HLC-FFR, HLC-HC4 | Non-filtered Diffusers | |||||
Healthcare, Laboratories, and Cleanrooms | Non-filtered Diffusers | HLC-LFD, HLC-CLF, HLC-FFR, HLC-HC4 | 3 weeks | |||||
Healthcare, Laboratories, and Cleanrooms | Non-filtered Diffusers | HLC-LFD, HLC-CLF, HLC-FFR, HLC-HC4 | Quick build requests require prior approval. | |||||
Healthcare, Laboratories, and Cleanrooms | Filtered Diffusers | HLC-GSL, HLC-GFR | Filtered Diffusers | |||||
Healthcare, Laboratories, and Cleanrooms | Filtered Diffusers | HLC-GSL, HLC-GFR | 6 weeks | |||||
Healthcare, Laboratories, and Cleanrooms | Filtered Diffusers | HLC-GSL, HLC-GFR | Quick build requests require prior approval. | |||||
Healthcare, Laboratories, and Cleanrooms | Operating Room Systems | HLC-SAC, HLC-HCG, HLC-MPA | Operating Room Systems | |||||
Healthcare, Laboratories, and Cleanrooms | Operating Room Systems | HLC-SAC, HLC-HCG, HLC-MPA | 8 weeks | |||||
Healthcare, Laboratories, and Cleanrooms | Operating Room Systems | HLC-SAC, HLC-HCG, HLC-MPA | Lead time is from date of approved engineering drawings. | |||||
Healthcare, Laboratories, and Cleanrooms | Operating Room Systems with Structual Equipment Supports | HLC-SPA | Operating Room Systems with Structual Equipment Supports | |||||
Healthcare, Laboratories, and Cleanrooms | Operating Room Systems with Structual Equipment Supports | HLC-SPA | 12 weeks | |||||
Healthcare, Laboratories, and Cleanrooms | Operating Room Systems with Structual Equipment Supports | HLC-SPA | Lead time is from date of approved engineering drawings. | |||||
Healthcare, Laboratories, and Cleanrooms | Fan Filter Diffusers | HLC-FPS, HLC-FPR, HLC-FPI, HLC-FPC | Fan Filter Diffusers | |||||
Healthcare, Laboratories, and Cleanrooms | Fan Filter Diffusers | HLC-FPS, HLC-FPR, HLC-FPI, HLC-FPC | 6 weeks | |||||
Healthcare, Laboratories, and Cleanrooms | Fan Filter Diffusers | HLC-FPS, HLC-FPR, HLC-FPI, HLC-FPC | Quick build requests require prior approval. | |||||
Healthcare, Laboratories, and Cleanrooms | High-efficency Filters (HLC-FILTER) | Stocked HEPA filters (48x24, 48x12, 36x24, 24x24)ULPA, High Flow HEPA, & non-stocked HEPA Filters | High-efficency Filters (HLC-FILTER) | |||||
Healthcare, Laboratories, and Cleanrooms | High-efficency Filters (HLC-FILTER) | Stocked HEPA filters (48x24, 48x12, 36x24, 24x24) | 1 weeks | |||||
Healthcare, Laboratories, and Cleanrooms | High-efficency Filters (HLC-FILTER) | ULPA, High Flow HEPA, & non-stocked HEPA Filters | 10 weeks | |||||
Healthcare, Laboratories, and Cleanrooms | High-efficency Filters (HLC-FILTER) | ULPA, High Flow HEPA, & non-stocked HEPA Filters | Quick builds are unavailable. |